Ken started work on the inflow of the ditch. The neighbors’ cattle make a huge mess and destroy the ditch every summer, so we’re going to install metal culvert pipes up past the gate where the cattle walk. I hope that this’ll prevent the water loss that happens when they smash the ditch sides.
Our first task was to dig out and measure the slope. Enos was back on Sunday, and in about 2.5 hours, he had cleared the entire north fenceline of rocks, put the loose rocks back on the rock wall, and leveled the whole line. He is a very skilled equipment operator. Larry will be back on Monday, and by then, he can start setting the posts for the north line.