More Solar Work

,

On August 25th, the heat dump loop was completed. Next, we had to work on the actual panel mounting structure. The first step was to get the blocks that would provide the spacing for the braces. That was finished on September 11th. The next day, we started the mounting structure.

With the blocks secured, we installed the mounting frames themselves. We have very high winds at times, so these mounting frames had to be very sturdy. They’re bolted through the entire roof to the main structure of the garage. By the 12th, the structure was completely secured.

The roof is being prepped for panel mounts.
The panel mounting frames are securely installed on the roof.
Some copper pipes or conduits are running from the roof down to the ground.